Assume every activity begins at earliest start
date:
|
|
|
In
each time period, calculate:
|
|
|
resources required
|
|
|
resources available
|
|
|
Identify
shortage / surplus resources
|
|
|
Adjust
schedule
|
|
|
acquire extra staff (e.g., consultants)
|
|
|
rearrange schedule (e.g., change
vacations)
|
|
|
change order of carrying out activities
|
|
|
The earlier that a problem is known, the
easier it is to fix.
|