Experience with Critical Path Method
Administrative computing department at Dartmouth used the
Critical Path Method for implementation phase of major
projects.
Experience:  Elapsed time to complete projects was consistently
25% to 40% longer than predicted by model.
Analysis:
   Some tasks not anticipated (incomplete understanding)
   Some tasks had to be redone (change of requirements,
     technical changes)
   Key personnel on many activities (schedule conflicts)
   System ZZZ (non-billable hours)