Administrative computing department at
Dartmouth used the
|
|
|
Critical Path Method for implementation phase
of major
|
|
|
projects.
|
|
|
Experience: Elapsed time to complete projects was
consistently
|
|
25%
to 40% longer than predicted by model.
|
|
|
Analysis:
|
|
|
• Some tasks not anticipated (incomplete understanding)
|
|
|
• Some tasks had to be redone (change of requirements,
|
|
|
technical changes)
|
|
|
• Key personnel on many activities (schedule conflicts)
|
|
|
• System ZZZ (non-billable hours)
|
|