Project Planning Methods
The Critical Path Method, Gantt charts, Activity bar charts, etc.
are roughly equivalent.
These methods are best when:
   Model is updated regularly (e.g., monthly)
   The structure of the project is well understood
   The time estimates are reliable
   Activities do not share resources